Deliverable 3 — Development Budget

Project: CivicLink Method: Velocity-based budgeting (Scrum) Currency: USD (with COP equivalents at indicative rate) Date of estimate: April 2026


1. Method

Per the workshop reference text, the budget is derived as:

Budget = Cost per Sprint × Number of Sprints + Tools + Equipment + Contingency

with effort estimated in story points and converted to elapsed sprints using velocity:

Number of Sprints = ⌈ Total Story Points / Velocity ⌉

Story points are not hours, but converted to role-hours per sprint using each role's allocation in the team. Hourly rates are then applied per role.


2. Inputs

Input Value Source
Total backlog 218 SP Backlog
Steady-state velocity 45 SP / sprint Industry benchmark for a 6-dev team, validated in retrospectives
Sprint length 2 weeks (10 working days, 80 working hours per FTE) Standard Scrum
Number of sprints ⌈218 / 45⌉ = 5 Computed
Project duration 10 weeks (+1-week Sprint 0 for setup) Computed
Team FTE composition 7 roles, mixed allocation Section 3

3. Team and Allocations

Role Allocation Hours over 10 weeks Why this allocation
Project Manager 60% 240 Ceremonies, stakeholder mgmt, budget tracking — not hands-on coding
Tech Lead / Solution Architect 100% 400 Architecture, code reviews, mentoring, hardest stories
Frontend Developer #1 100% 400 Citizen Portal
Frontend Developer #2 100% 400 Admin Dashboard
Backend Developer #1 100% 400 requests-service, departments-service
Backend Developer #2 100% 400 identity-service, notifications-service, reports-service
DevOps Engineer 80% 320 CI/CD, infra, observability, release engineering
QA Engineer 100% 400 Test plans, automation, UAT support
UX/UI Designer 50% 200 Front-loaded in Sprints 0–2, lighter from Sprint 3
Total 3,160

Note. The PM, Tech Lead, DevOps, QA, and UX roles can be staffed by more than one person at lower allocations — the totals (hours and cost) are what matter for the budget.


4. Hourly Rates (Colombian market, 2026)

Rates are blended (mid + senior) and consistent with public salary surveys for Colombia. They are fully loaded (gross salary + social contributions + overhead).

Role Hourly Rate (USD) Hourly Rate (COP @ 4,200)
Project Manager $40 $168,000
Tech Lead / Solution Architect $60 $252,000
Frontend Developer (blended) $35 $147,000
Backend Developer (blended) $38 $159,600
DevOps Engineer $45 $189,000
QA Engineer $28 $117,600
UX/UI Designer $35 $147,000

5. Labor Cost Breakdown

Role Hours Rate (USD) Cost (USD)
Project Manager (60%) 240 $40 $9,600
Tech Lead / Architect 400 $60 $24,000
Frontend Dev #1 400 $35 $14,000
Frontend Dev #2 400 $35 $14,000
Backend Dev #1 400 $38 $15,200
Backend Dev #2 400 $38 $15,200
DevOps Engineer (80%) 320 $45 $14,400
QA Engineer 400 $28 $11,200
UX/UI Designer (50%) 200 $35 $7,000
Subtotal labor 3,160 $124,600

6. Other Costs

6.1 Tools and Licenses (10 weeks)

Item Tier Cost (USD)
GitHub Team Per seat × 9 $200
Auth0 Essentials Up to 1k MAUs $500
Atlassian Jira + Confluence 10 seats $300
Figma 3 editor seats $150
Sentry Team 1 organization $300
Datadog / Grafana Cloud Pro 5 hosts $500
AWS dev + staging (compute, RDS, S3, MSK basic, CloudWatch) mixed $2,500
Domains, SSL, miscellaneous $200
Subtotal $4,650

6.2 Equipment and Onboarding

Item Cost (USD)
Hardware top-up / peripherals (3 × $500 average) $1,500
Onboarding, training material, kickoff workshop $500
Subtotal $2,000

6.3 Contingency Reserve

15% of (labor + tools + equipment) = 0.15 × ($124,600 + $4,650 + $2,000) = $19,688.

Contingency covers: scope creep on the Could epic (E8), velocity dips during the first sprint, surprises in the Carpeta Ciudadana integration, and minor rate variations.


7. Total Project Cost

Category Amount (USD) Amount (COP @ 4,200)
Labor $124,600 COP 523,320,000
Tools & licenses $4,650 COP 19,530,000
Equipment & onboarding $2,000 COP 8,400,000
Contingency (15%) $19,688 COP 82,689,600
Total (point estimate) $150,938 **~ COP 633,940,000**

7.1 Range (sensitivity)

Applying ±15% to capture rate volatility, velocity uncertainty, and scope drift:

Scenario Total (USD) Total (COP)
Optimistic (P10) $128,300 COP 538,860,000
Likely (P50) $150,938 COP 633,940,000
Pessimistic (P90) $173,580 COP 729,030,000

7.2 Cost per Sprint

Cost per Sprint ≈ $124,600 / 5 = $24,920 (labor only)
Fully loaded per sprint ≈ $150,938 / 5 = $30,188

This means each sprint delivers ≈ 45 SP for $30k → **$670 per story point** (fully loaded). Useful for change requests: a new 5 SP story costs roughly $3,350.


8. Sensitivity and Trade-offs

Lever Impact
Drop the Could epic (E8, 21 SP) Saves ~$14,000 (≈ half a sprint)
Cut UX/UI from 50% to 25% Saves $3,500 but risks usability
Replace one Senior dev with a Mid dev (-$10/h) Saves ~$4,000, possibly +1 sprint
Add a sixth sprint for hardening +$30k, raises confidence to ~95%
Move from EKS managed control plane to self-hosted K3s Saves ~$700 in cloud, adds DevOps load

9. Assumptions

  1. Team is fully staffed from day one of Sprint 1; Sprint 0 is shared across roles and budgeted within the labor totals.
  2. Velocity stabilises at 45 SP by Sprint 2; Sprint 1 plans for ~45 with low buffer because the team is experienced.
  3. No travel costs; team is co-located in Bogotá or fully remote with daily overlap.
  4. Production operations are out of scope of this project budget. Running CivicLink in production is a separate operations budget owned by the municipality.
  5. Auth0 Essentials tier is sufficient for the build phase. Production volume might require a larger plan.
  6. Government SSO integration (US-42) requires no paid integration — only OIDC config — and is treated as a Could.
  7. Hourly rates reflect the Colombian market in 2026; mid+senior blend.
  8. Photo storage at MVP scale stays under 50 GB — S3 cost is negligible (<$10/month) and is bundled in the cloud line.

10. Risk Register (cost-relevant)

ID Risk Likelihood Impact (USD) Mitigation
R1 Carpeta Ciudadana integration delayed or paid Medium +$8,000 Treated as Could; buffered
R2 Velocity dips below 35 SP for 2 sprints Medium +$25,000 Buffer + scope re-prioritisation
R3 A senior dev leaves mid-project Low +$10,000 Tech Lead absorbs; +1 sprint
R4 Cloud cost spike (load tests in staging) Low +$2,000 Rate-limit load tests, schedule off-hours
R5 Auth0 needs Professional plan early Low +$1,500 Cap MAUs; switch tier if needed
R6 Currency volatility (COP/USD) Medium ±10% Lock contracts in COP for local team
R7 Scope creep from stakeholders High +$15,000 MoSCoW + change-request priced at $670/SP

11. Acceptance of the Estimate

This budget is presented as a fixed-time, scoped backlog plan: the timeline (10 weeks + 1 setup) and the Must scope are committed; Should is expected; Could is conditional. If the municipality fixes the budget instead of the scope, the team will commit only the Must epics first and prioritise Should until budget is exhausted, in line with Scrum's fixed-budget mode described in the workshop reference.


12. Quick Reference

Question Answer
How long? 10 weeks (5 sprints × 2 weeks) + 1 week Sprint 0
How big a team? 7 roles, 3,160 total hours
How much? USD $150,938 point estimate, $128k – $174k range
Per sprint? ~$30,188 fully loaded
Per story point? ~$670 fully loaded
What's not included? Production operations, third-party SaaS production tiers, marketing